Sterling Ridge Estates Updates – April 2014

Lot 27:

Drywall was hung in late February. Installation on cabinets has begun this week!

4-2-14 (4)

 

Lot 41

The framing is moving along nicely, with ceiling and roof underway. Window wells are also being installed.

 

4-5-14 (1)

 

4-5-14 (3)

 

 

Lot 47

Upper walls are being framed. Later this week framing will also begin on the rear deck and ceiling/roof.

4-1-14 (8) 4-1-14 (9) 4-1-14 (10)